A typical job on a typical house, not a real customer: a single-storey rear extension with a new kitchen on a Victorian mid-terrace in Brent. Every figure is from the same engine that prices your report.

Start yours · £12

Cost My Extension

Single-storey rear extension

Address
Sample house, Kensal Rise, NW10 3XX
Borough
Brent
Written
20 October 2026
Pricing basis
2026-10-20.1

Expected cost: building work, fit-out and fees, VAT included

£120,500

Likely between £95,500 to £146,000. Building work alone £52,000 to £85,500 for about 20 m².

Expected £120,500
£95,500£146,000
Budget to have available
£154,500
The top of the likely range plus £8,000 contingency to hold back.
Planning
Larger home extension: prior approval needed
Time
23 to 43 weeks
From today to moving back in, 8 to 16 of them on site.
Worth knowing about
Party wall noticesPublic sewer nearby (to check)
Each is explained under planning and permissions.

Expect a 20 m² single-storey rear extension with a new kitchen and bifold doors to cost about £120,500 all in, most likely somewhere between £95,500 to £146,000. That covers the building work, the kitchen and doors, and the professional and council fees; with the contingency you should hold back on top, have £154,500 available. A rear extension of up to 3 m on a terrace is usually permitted development; yours is 4 m, which puts it in the prior approval route, where the council asks the neighbours before it can go ahead. Two party walls are affected, so budget for party wall surveyors unless both neighbours consent in writing. From first sketch to moving back in, allow 23 to 43 weeks.

01

The house

The EPC register has this as a 1900 to 1929 mid-terrace house of about 94 m² with no extension recorded, which is what you told us and what the street suggests: a Victorian or Edwardian terrace with a back addition. The planning register shows no conservation area at this postcode and the only Article 4 direction recorded in Brent concerns houses in multiple occupation, not extensions, so it does not touch you. The flood zone is 1, the lowest. None of that is a survey of your house: it tells us the rules that apply, not the state of the drains or the footings.

House
Mid-terrace house
On the EPC register
Mid-Terrace, House
Floor area on record
94 m²
Age band
1900-1929
Conservation area
No
Article 4 direction
None affecting extensions
Flood zone
Zone 1
NeighbourNeighbourHouseParty wallParty wallGarden boundaryYour extension5 m4 m
Plan, to scale. Your extension in red, 4 m deep by 5 m wide.

Checked: postcodes.io (ok); EPC register (ok); planning.data.gov.uk (ok). Constraint checks use the postcode's centre point, so they describe the area, not the exact plot.

02

The cost

inc VAT
Building work53% · £68,500Fit-out you chose29% · £37,500Fees and approvals12% · £14,500Contingency6% · £8,000
Where the expected £120,500 goes, with the £8,000 contingency beside it: money to have available, not money you will certainly spend.

Most of the money goes into the shell: the foundations and slab on London clay, the new walls with a long steel to open up the back of the house, and the roof and glazing. The kitchen, at £16,000 to £28,000, is the biggest single choice you have made, and the party wall line only becomes real if a neighbour dissents. What would push this job towards the top of its range is the ground: drains that are not where the drawing says, or footings that need to go deeper. The choice worth most is the depth: one metre shallower, at 3 m, would bring the expected cost down by £10,500 and take you back inside permitted development.

Building work

Extension: groundworks, structure, roof, glazing, first and second fixAbout 20 m². Broken down by trade under where the money goes.£52,000 to £85,400

Fit-out you chose

New kitchen: units, worktops, appliances, fitting£16,000 to £28,000
Bifold or sliding doors£7,000 to £11,000
Knocking through: steel beam, making good£4,500 to £8,000

Fees and approvals

Architect or designer: drawings, planning and building regulations package£4,200 to £11,100
Structural engineer: calculations and beam design£1,000 to £2,500
Council prior approval feeStatutory fee plus the Planning Portal's service charge.£334
Building control: plan check and inspections£1,000 to £1,800
Party wall surveyors (2 neighbours, if they dissent)Zero if your neighbours consent in writing. Budget the top figure if relations are cool.£0 to £6,000
Thames Water build-over agreement (if a public sewer is within 3 m)£0 to £1,200
Expected costLikely £95,500 to £146,000£120,500
Contingency to hold back (12% of the building work)Not a cost you will certainly pay: money to have available if something unforeseen turns up.£8,000
Budget to have availableThe top of the likely range plus the contingency.£154,500

The likely range allows for the lines moving partly together, as they do on real jobs. If every line came in at its cheapest at once the total would be £86,000; at its dearest, £155,500. All figures include VAT at 20%. Builders often quote without VAT, so add 20% to any quote that says 'plus VAT' before comparing it with this report.

04

Planning and permissions

4 mheight limitPermitteddevelopmentPriorapprovalPlanningapplicationHouse03 m6 mYours, 4 m deep
Larger home extension: prior approval needed.

Larger home extension: prior approval needed. The standard permitted development limit for a rear extension on an attached house is 3 m. Between 3 m and 6 m you can use the larger home extension route: you tell the council before you start, it writes to the neighbours, and if nobody objects within 21 days it is deemed approved after 42 days. If a neighbour objects, the council decides whether the effect on their amenity is acceptable. The height rules still apply: no higher than 4 m, and eaves no higher than 3 m within 2 m of the boundary, which on a terrace means a flat roof at about 3 m at the fence. After the work, a lawful development certificate is worth having for when you sell.

  • ✓ passConservation area. The planning register shows no conservation area at this postcode. (planning.data.gov.uk conservation-area dataset)
  • ✓ passArticle 4 direction. The only Article 4 direction recorded here (Article 4 for HMOs) concerns a different kind of development, not householder extensions or lofts. (planning.data.gov.uk)
  • ? checkRear projection. 4 m is beyond the standard 3 m but within the 6 m larger home extension allowance. That route needs prior approval from the council, with neighbours consulted, and is not available in a conservation area. (GPDO 2015 Sch. 2 Pt 1 A.1(g), A.4)
  • ? checkHeight. Single storey: no higher than 4 m, and eaves no higher than 3 m if within 2 m of a boundary. A 3 m flat roof at the boundary is the usual answer on a terrace. (GPDO 2015 Sch. 2 Pt 1 A.1(f), A.1(i))
  • ? checkHalf the garden. Extensions and outbuildings together may not cover more than half the land around the original house. (GPDO 2015 Sch. 2 Pt 1 A.1(b))
  • ? checkMaterials. Materials must be of similar appearance to the existing house, except for a conservatory. (GPDO 2015 Sch. 2 Pt 1 A.3(a))

What else applies

  • Party Wall etc. Act 1996 applies

    Building up to or astride the boundary needs a line of junction notice (1 month). Digging foundations within 3 m of a neighbour's structure, and deeper than theirs, needs a notice of adjacent excavation (1 month). Each neighbour can consent or dissent; dissent means surveyors, which you pay for.

    Nothing if neighbours consent in writing within 14 days. Silence counts as dissent. One agreed surveyor runs £700 to £1,800 plus VAT; one each, £1,500 to £3,500 in total. You pay.

  • Building Regulations approval applies

    Every extension and loft conversion needs building control sign-off: foundations, structure, fire escape, insulation, drainage, electrics. Use the council or a registered building control approver. Ask for the completion certificate at the end; you will need it to sell.

  • Structural engineer applies

    Steels for the opening into the house, the roof and any glazing spans need calculations.

  • Thames Water build-over agreement check

    If a public sewer runs within 3 m of the new foundations, Thames Water must agree the design first. Many London terraces have a shared sewer at the rear. Your designer checks the sewer map early.

    Thames Water's fee is £130 for a small pipe or £490 plus a CCTV survey for a larger one; the extra foundation work is the real cost. Allow 3 weeks.

  • Community Infrastructure Levy does not apply

    Householder extensions under 100 m² that do not create a new dwelling are exempt, and larger ones can claim the self-build exemption, but only if the forms are filed before work starts.

05

Timeline

About 23 to 43 weeks from today to moving back in, of which 8 to 16 weeks on site. Builders are often booked 3 to 6 months ahead, which can add to this.

010203040506In all, 23 to 43 weeks081624324048Weeks from today
Solid lines are the shorter estimate, dashed the longer. The build on site is in red.
  1. 01Design and drawings4 to 8 wkMeasured survey, sketch options, the drawings for planning or the lawful development certificate.
  2. 02Prior approval6 to 8 wkThe council consults neighbours for 21 days and must decide within 42 days, or approval is deemed.
  3. 03Structural design, building regulations drawings, tender4 to 8 wkEngineer's calculations, the building regulations package, and getting three like-for-like quotes.
  4. 04Party wall notices4 to 10 wkRuns alongside tender. One month for line of junction or excavation notices, two months for a party structure notice, longer if a neighbour dissents.
  5. 05Build8 to 16 wkFoundations, drainage, walls, roof, glazing, first fix, plaster, second fix, kitchen or bathroom, decoration.
  6. 06Completion and sign-off1 to 3 wkSnagging, building control's final inspection, the completion certificate and the party wall award closed.
07

Before you get quotes

Risks for this job

  • The 4 m depth relies on prior approval. If either neighbour objects and the council sides with them, the fallback is 3 m, which changes the kitchen layout. Design for both from the start.
  • A long steel across the back of a Victorian terrace needs padstones and often a goalpost frame. If the engineer finds the existing brickwork is soft, the cost of that line rises.
  • Drains on terraces of this age often run across the back garden. If a shared sewer is within 3 m of the new foundations, Thames Water must agree the build-over before you dig.
  • Two party walls means two sets of notices. One dissenting neighbour adds about £1,500 to £3,000 and four to eight weeks.
  • Bifold doors across a 5 m opening are heavy and need a stiff lintel; cheap frames warp. The glazing specification is the single biggest quality decision in this job.
  • Builders in north-west London are booking three to six months ahead. The timeline assumes you can start when the paperwork is ready.

Questions to ask anyone who quotes

  1. Is your price fixed, or an estimate subject to measurement, and what is excluded from it?
  2. Does the price include VAT, and are you VAT registered?
  3. Who is the structural engineer, and is their design included or extra?
  4. Which items are provisional sums, and what are they for?
  5. How will you handle the drains if they are not where the drawing shows?
  6. What is your payment schedule, and is it tied to stages of work rather than dates?
  7. Who is on site day to day, and how many other jobs will you be running?
  8. Can I speak to two customers whose rear extensions you finished in the last year?

Next steps

  1. Get a measured survey and sketch options from an architect or designer, including a 3 m version.
  2. Ask the designer to confirm the roof height and eaves at the boundary against the permitted development rules.
  3. Submit the prior approval notification and, in parallel, get the structural design and building regulations drawings done.
  4. Serve party wall notices on both neighbours as soon as the drawings are fixed.
  5. Send the same drawings and specification to three builders and compare like for like.
  6. Hold the contingency in a separate account and do not touch it for upgrades.

This report is an informed estimate built from public data about your property and current London build costs. It is not a survey, a quote, a valuation or planning advice. Always get written quotes and, where noted, professional advice before committing to work.

Pricing basis 2026-10-20.1. Planning rules from the GPDO 2015 as amended, checked October 2026.

Contains OS data © Crown copyright and database right 2026. Contains Royal Mail data © Royal Mail copyright and database right 2026. Contains National Statistics data © Crown copyright and database right 2026. Contains public sector information licensed under the Open Government Licence v3.0 (planning.data.gov.uk; Energy Performance of Buildings data, MHCLG).